List of steps
(Total number of steps: 69)
Meet Department of Planning and Investment (DPI)
Define location  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
18
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain planning license  (3)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (3)
Obtain approval of master plan and architectural plan  (3)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land lease contract land use right certificate  (3)
Attend on-site title plan verification  (1)
Obtain fire prevention and fighting approval of conceptual plans  (2)
Obtain opinions on conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
69
Collect construction permit
(last modified: 5/26/2015)

Contact details

Entity in charge

HCMC Construction Department

60 Truong Dinh Street, Ward 7, District 3 , HCMC
Tel: +84 283 932 5945
Tel. 1: +84 283 932 5269
Email: sxd@tphcm.gov.vn
Website: http://www.constructiondpt.hochiminhcity.gov.vn

Unit in charge

Reception and Release Unit

Mon: 07:30-11:30, 13:00-16:30
Tue: 07:30-11:30, 13:00-16:30
Wed: 07:30-11:30, 13:00-16:30
Thu: 07:30-11:30, 13:00-16:30
Fri: 07:30-11:30
Sat: 07:30-11:30

Person in charge

Mr. Ho Minh Tam

Officer
Tel: +84 83 932 6214 (ext 500)

Expected results

Construction permit Construction permit

Requirements

Representatives
For all investors:
1. 01 - Libre deuda de patente
Receipt of application for construction permit (original)
2. 01 - Libre deuda de patente
Payment receipt for construction permit (original)
3. 01 - Libre deuda de patente
Passport or Vietnamese ID card (original)
(of the person collecting result to present at the counter)
If the investors authorize the other person to collect result, supplement:
1. Power of attorney
Power of attorney (original)

Time frame

Waiting time in queue: Min. 5mn - Max. 15mn
Attention at counter: Min. 5mn - Max. 10mn

Legal justification

1. Circular No. 13/2013/TT-BXD, Promulgating the verification, appraisal and approval for construction designs
Circular No. 13/2013/TT-BXD, Promulgating the verification, appraisal and approval for construction designs
Article 3
2. Decree 15/2013/ND-CP dated February 6, 2013 of the Government on quality management of construction works
Decree 15/2013/ND-CP dated February 6, 2013 of the Government on quality management of construction works
Article 21.1

Additional information

According to Article 72, Law of Construction No. 16/2003/QH11, one of conditions the investors must have before starting construction work (after being granted construction permit) is to have the approved construction drawing designs of items or works.
Article 3, Circular 13/2013/TT-BXD, guiding the investors to carry out these tasks:
- Case of one-step design: Investors will organize appraisal and submit to the person deciding investment for approval of construction drawings design together with the economic-technical report on works construction.
- Case of two-step design, three-step design or other design which are carried out following the fundamental design: Investors will organize appraisal and approval for technical deign (in case of the three-step design), construction drawings design (in case of the two-step design) and other designs which are carried out following fundamental design.
In the course of appraisal, as necessary, the investors may hire organization or individual which is eligible for capability to perform verification over contents servicing appraisal and approval for design.
For works using entire or part of capital from state budget, works using capital originated from state budget, works invested by capital for concentrated capital construction, works invested under forms of: Building-transfer (BT), building-operation-transfer (BOT), building-transfer-operation (BTO), public-private partnership (PPP) and works invested by other mixed capital sources as prescribed in Clause 1 Article 21 of the Decree 15/2013/ND-CP: Investors will submit construction-specialized agencies for verifying design as prescribed in Article 4 and Article 5 of this Circular before approving design.
The construction drawings design must be certified by investor or an authorized representative of investor with signature and sealed as being approved according to the Form of Annex No. 4 enclosed with this Circular on each drawing sheet before putting into construction, even case of the one-step design after the person competent to decision on investment approved.
The person organizing appraisal, verification and approval for design must be responsible for his/her result of appraisal, verification and approval for the design.

Recourse: HCMC Construction Department

Entity in charge

HCMC Construction Department

60 Truong Dinh Street, Ward 7, District 3 , HCMC
Tel: +84 283 932 5945
Tel. 1: +84 283 932 5269
Email: sxd@tphcm.gov.vn
Website: http://www.constructiondpt.hochiminhcity.gov.vn

Unit in charge

Reception Division

Mon: 07:30-11:30, 13:00-17:00
Tue: 07:30-11:30, 13:00-17:00
Wed: 07:30-11:30, 13:00-17:00
Thu: 07:30-11:30, 13:00-17:00
Fri: 07:30-11:30, 13:00-17:00

Person in charge

Mr. Tran Hoang Hai

Inspection Officer
Tel: +84 83 932 5945 (ext 100)
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License