List of steps
(Total number of steps: 69)
Meet Department of Planning and Investment (DPI)
Define location  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
18
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain planning license  (3)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (3)
Obtain approval of master plan and architectural plan  (3)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land lease contract land use right certificate  (3)
Attend on-site title plan verification  (1)
Obtain fire prevention and fighting approval of conceptual plans  (2)
Obtain opinions on conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
47
Obtain approval of compensation and resettlement plan
(last modified: 5/26/2015)

Contact details

Entity in charge

Any District People's Committee

List of District and Commune People's Committees in HCMC List of District and Commune People's Committees in HCMC

Expected results

Written approval of compensation and resettlement plan Written approval of compensation and resettlement plan

Legal justification

1. Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Article 69.3

Additional information

The People’s Committee which has the competence shall issue a decision on land recovery and a decision on approval of the plans for compensation, support and resettlement in the same day;