List of steps
(Total number of steps: 61)
Meet Management Authority for Southern Area Development (MASD)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
17
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain fire prevention and fighting approval for 1/500 construction planning project  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (2)
Obtain master plan and architectural plan approval  (2)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Attend on-site title plan verification  (1)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land use right, house and land-attached asset ownership certificate  (3)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
59
Prepare drawings profile
(last modified: 1/13/2015)

Contact details

Entity in charge

Any authorized construction consulting company


List of construction consulting companies (not exhaustive) List of construction consulting companies (not exhaustive)

Expected results

Master plan drawing of project or master plan of separate phases of project 1/100-1/500 scale 01 - Master plan drawing of project or master plan of separate phases of project 1/100-1/500 scale
Drawings of construction items' plan, scale 1/100 - 1/500 01 - Drawings of construction items' plan, scale 1/100 - 1/500
Main vertical and sectional drawings of construction items,scale 1/50-1/200 01 - Main vertical and sectional drawings of construction items,scale 1/50-1/200
Drawings of base footing of construction items, scale 1/100 - 1/200 01 - Drawings of base footing of construction items, scale 1/100 - 1/200
Sectional drawings of footing of construction items, scale 1/50 01 - Sectional drawings of footing of construction items, scale 1/50
Diagrams of technical infrastructure works 01 - Diagrams of technical infrastructure works
Practising certificate 01 - Practising certificate

Costs

Cost based on the scale and complexity of the project

Additional information

Investors shall hire a consultant company or may themselves carry out surveying and designing works when they satisfy the conditions on capability for execution of building works.
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License