List of steps
(Total number of steps: 61)
Meet Management Authority for Southern Area Development (MASD)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
17
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain fire prevention and fighting approval for 1/500 construction planning project  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (2)
Obtain master plan and architectural plan approval  (2)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Attend on-site title plan verification  (1)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land use right, house and land-attached asset ownership certificate  (3)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
43
Pay compensation and implement land clearance upon approved plan
(last modified: 1/13/2015)

Contact details

Entity in charge

Any District People's Committee inside MASD's area


Addresses of The people's Committees of Districts inside MASD Addresses of The people's Committees of Districts inside MASD

Legal justification

1. Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Article 69.3b

Additional information

Within three (3) days after receiving an approved compensation, support and resettlement plan, the compensation and ground clearance organization shall coordinate with the commune-level People's Committee in disseminating the decision approving the compensation plan and publicly posting it up at the head office of the commune-level People's Committee and public-activity place of the residential area where exists the to-be-recovered land; and send compensation, support and resettlement decisions to persons having to-be-recovered land, indicating the compensation and support level, arrangement of a resettlement house or land (if any), time and place for paying the compensation and support money, and time for handing over the recovered land to the compensation and ground clearance organization.
Compensation, support and resettlement councils or Committee for compensation and land clearance shall pay compensation and support money and arrange places for resettlement.
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License