List of steps
(Total number of steps: 61)
Meet Management Authority for Southern Area Development (MASD)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
17
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain fire prevention and fighting approval for 1/500 construction planning project  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (2)
Obtain master plan and architectural plan approval  (2)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Attend on-site title plan verification  (1)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land use right, house and land-attached asset ownership certificate  (3)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
40
Attend meetings of Council of compensation, support and resettlement
(last modified: 1/13/2015)

Contact details

Entity in charge

Any District People's Committee inside MASD's area


Addresses of The people's Committees of Districts inside MASD Addresses of The people's Committees of Districts inside MASD

Expected results

Compensation and resettlement plan Compensation and resettlement plan

Requirements

1. 01 - Libre deuda de patente
Several meetings of compensation council and other activities requested by the Council

Legal justification

1. Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Article 69.2

Additional information

The organization in charge of compensation and ground clearance shall make the plan for compensation, support and resettlement and coordinate with the commune-level People’s Committee in the locality to conduct consultations on the plans for compensation, support and resettlement in the forms of meetings with land users living in the recovered area, posting up the plan for compensation, support and resettlement at offices of the commune-level People’s Committee and at common public places of the residential areas of which land is recovered.
The consultation results must be recorded in minutes which are certified by representatives of the commune-level People’s Committee and Vietnam Fatherland Front, and users of recovered land.
The organization in charge of compensation and ground clearance shall make a written summarization of opinions which clearly specifies the numbers of opinions for, against and other opinions regarding the plans for compensation, support and resettlement; coordinate with the commune-level People’s Committee in the locality in organizing dialogues with those who have objections on the plans for compensation, support and resettlement; and improve the plans for submission to competent agencies.
Competent agencies shall appraise the plans for compensation, support and resettlement before submitting them to the competent People’s Committee for decision on land recovery.