List of steps
(Total number of steps: 61)
Meet Management Authority for Southern Area Development (MASD)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
17
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain fire prevention and fighting approval for 1/500 construction planning project  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (2)
Obtain master plan and architectural plan approval  (2)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Attend on-site title plan verification  (1)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land use right, house and land-attached asset ownership certificate  (3)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
12
Collect approval of investment intent
(last modified: 1/13/2015)

Contact details

Entity in charge

Department of Natural Resources and Environment (DONRE)

63 Ly Tu Trong, District 1 , Ho Chi Minh
Tel: +84 28 382 936 61
Tel. 1: +84 28 382 318 06
Email: stnmt@tphcm.gov.vn
Website: http://www.donre.hochiminhcity.gov.vn/

Expected results

Approval of Investment intent Approval of Investment intent
Written assessment of requirements for land use; conditions for land lease Written assessment of requirements for land use; conditions for land lease

Requirements

1.
Receipt of investment intent application (original)

Legal justification

1. Decision 19/2008/QD-UBND dated 21/03/2008 of People's Committee of Ho Chi Minh City providing Regulation on procedures of the land allocation, land leasing, changing purpose of land using in the area of Ho Chi Minh City
Decision 19/2008/QD-UBND dated 21/03/2008 of People's Committee of Ho Chi Minh City providing Regulation on procedures of the land allocation, land leasing, changing purpose of land using in the area of Ho Chi Minh City
Article 26.4.e.g