List of steps
(Total number of steps: 61)
Meet Management Authority for Southern Area Development (MASD)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
17
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain fire prevention and fighting approval for 1/500 construction planning project  (2)
Obtain 1/500-scale detailed construction-planning projects appraisal and approval  (2)
Obtain master plan and architectural plan approval  (2)
Obtain land recovery notice  (1)
Make plan for compensation, land clearance and resettlement  (3)
Obtain decision on land recovery  (1)
Pay compensation and implement land clearance upon approved plan  (1)
Obtain decision on land lease  (2)
Attend on-site title plan verification  (1)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land use right, house and land-attached asset ownership certificate  (3)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
41
Obtain approval of compensation and resettlement plan
(last modified: 3/16/2015)

Contact details

Entity in charge

Management Authority of Southern Area Development (MASD)

9-11 Tan Phu Street, Tan Phu Ward, District 7 , Ho Chi Minh City
Tel: +84 282 245 5107
Tel. 1: +84 285 416 0077
Email: bqlkn@tphcm.gov.vn
Website: http://www.bqlkhunam.hochiminhcity.gov.vn

Unit in charge

MASD Office

Mon: 08:00-11:30, 13:00-16:30
Tue: 08:00-11:30, 13:00-16:30
Wed: 08:00-11:30, 13:00-16:30
Thu: 08:00-11:30, 13:00-16:30
Fri: 08:00-11:30, 13:00-16:30

Person in charge

Ms. Nguyen Thi Bich Thao

Officer
Tel: +84 8 224 551 37
Email: thaontb@tphcm.gov.vn

Expected results

Written approval of compensation and resettlement plan Written approval of compensation and resettlement plan

Legal justification

1. Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Law on land No 45/2013/QH13 dated 29/11/2013 (EN)
Article 69.3

Additional information

The People’s Committee which has the competence shall issue a decision on land recovery and a decision on approval of the plans for compensation, support and resettlement in the same day;
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License