(Total number of steps: 44)
Meet HCMC Export Processing and Industrial Zones Authority (HEPZA)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Sign MOU on land lease  (1)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
15
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Sign land lease contract and obtain land use right certificate  (3)
Obtain authenticated copies of land use right certificate  (2)
Obtain approval on environmental impact assessment  (8)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (2)
Obtain opinions on conceptual plans  (4)
Obtain approval of fire prevention and fighting for technical design or construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
35
Prepare drawings profile
(last modified: 5/29/2015)

Costs

( ver detalles )

Espera hasta paso siguiente

Free of charge
10 days  -  15 days

Contact details

Entity in charge

Any authorized construction consulting company


List of construction consulting companies (not exhaustive) List of construction consulting companies (not exhaustive)

Expected results

Explanation of conceptual plans x2 Explanation of conceptual plans
Location map of land plot inside the industrial zone x2 01 - Location map of land plot inside the industrial zone
Master plan drawing of construction project x2 01 - Master plan drawing of construction project
Drawings of architectural plan x2 01 - Drawings of architectural plan
Drawings of major construction structure plan x2 01 - Drawings of major construction structure plan
Drawings of general planar infrastructure systems x2 01 - Drawings of general planar infrastructure systems
Practising certificate 01 - Practising certificate

Requirements

1. Consulting contract
Consulting contract (original)

Costs

Cost based on the scale and complexity of the project

Time frame

Waiting time until next step: Min. 10 days - Max. 15 days

Additional information

Investors shall hire a consultant company or may themselves carry out surveying and designing works when they satisfy the conditions on capability for execution of building works.