List of steps
(Total number of steps: 60)
Meet Investment & Construction Authority for Thu Thiem urbanized Area (ICA)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain map of current state of land plot  (1)
Obtain approval of investment intent  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of IRC  (2)
Make seal and notify seal specimen  (2)
17
Make seal
Obtain certificate of tax registration  (1)
Open bank account  (1)
Publish in National Business Registration Portal  (1)
Obtain approval of environment impact assessment report  (8)
Obtain planning certificate  (2)
Obtain planning license  (3)
Obtain appraisal and approval of 1/500-scale detailed construction-planning task  (3)
Obtain appraisal and approval of 1/500-scale detailed construction-planning projects  (3)
Obtain decision on land lease  (2)
Pay land rental  (1)
Make draft of land use right certificate  (1)
Sign land lease contract  (1)
Obtain land use right, house and land-attached asset ownership certificate  (3)
Attend on-site title plan verification  (1)
Obtain written recommendation on fire prevention and fighting solutions of conceptual plans  (2)
Obtain opinions on conceptual plans  (3)
Obtain approval of fire prevention and fighting for technical design/construction drawings  (3)
Obtain construction permit  (3)

Preview & Print

Properties
 
Verify the status of the application
(last modified: 13/01/2015)
This step is optional

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  35 mn
12 days  -  20 days

Contact details

Entity in charge

Investment & Construction Authority for Thu Thiem urbanized Area (ICA)

255 Tran Hung Dao street, Co Giang, District 1 , Ho Chi Minh City
Tel: +84 283 526 1299
Tel. 1: +84 283 526 1301
Email: [email protected], [email protected]
Website: http://www.thuthiem.hochiminhcity.gov.vn

Unit in charge

Investment Management Division

Mon: 07:30-11:30, 13:00-17:00
Tue: 07:30-11:30, 13:00-17:00
Wed: 07:30-11:30, 13:00-17:00
Thu: 07:30-11:30, 13:00-17:00
Fri: 07:30-11:30, 13:00-17:00

Person in charge

Mr. Le Chi Tam

Officer
Tel: 84 83 526 1299, 84 83 526 1271
Email: [email protected], [email protected]

Expected results

ICA request for additional information 01 - ICA request for additional information

Time frame

Waiting time in queue: Min.  5mn - Max. 15mn
Attention at counter: Min.  5mn - Max.  20mn
Waiting time until next step: Min.  12 days - Max.  20 days

Additional information

Within three working days, Thu Thiem ICA will check the application file. If the application file is incomplete, ICA will notify the investor in writing which amendments or additions are needed for the application to be accepted for assessment. The time for issuance of the Investment Certificate will be recounted from the date of submission of the additional documents.

Recourse: Investment & Construction Authority for Thu Thiem urbanized Area (ICA)

Entity in charge

Investment & Construction Authority for Thu Thiem urbanized Area (ICA)

255 Tran Hung Dao street, Co Giang, District 1 , Ho Chi Minh City
Tel: +84 283 526 1299
Tel. 1: +84 283 526 1301
Email: [email protected], [email protected]
Website: http://www.thuthiem.hochiminhcity.gov.vn

Unit in charge

Thu Thiem ICA Office

Mon: 08:30-10:30, 13:30-16:00
Tue: 08:30-10:30, 13:30-16:00
Wed: 08:30-10:30, 13:30-16:00
Thu: 08:30-10:30, 13:30-16:00
Fri: 08:30-10:30, 13:30-16:00

Person in charge

Mr. Vo Tuan Thanh

Officer
Tel: 84 83 526 1299, 84 83 526 1271
Email: [email protected], [email protected]
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License